Glasgow CityElectricity Act 1989ELECTRICITY ACT 1989TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997-4.23339857.473520IV3 5NX2012-04-162012-03-02IV35NXG28LU-4.26484355.857406G2 8LUHighlandTSO (The Stationery Office), St Crispins, Duke Street, Norwich, NR3 1PD, 01603 622211, customer.services@tso.co.uk270634343

Scottish Hydro Electric Transmission Limited

ELECTRICITY ACT 1989
TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997
THE ELECTRICITY WORKS (ENVIRONMENTAL IMPACT ASSESSMENT) (SCOTLAND) REGULATIONS 2000
THE ELECTRICITY (APPLICATIONS FOR CONSENT) REGULATIONS 1990

Notice is hereby given that additional information has been received by Scottish Ministers relative to the application under Section 37 and Schedule 8 of The Electricity Act 1989 for consent to install and keep installed, a proposed upgraded replacement 132kV AC double circuit, overhead, steel tower, transmission line between proposed Tower 3 at Corriemoillie, by Lochluichart, Ross-shire (Grid Reference NH 3491 6354) and proposed terminal Tower 97 at the proposed Dunmore Cable Termination Compound, by Beauly, Inverness-shire (Grid Reference NH 5067 4735)

Copies of this information have been forwarded to The Highland Council to be made available for public inspection by being placed on the planning register.

Any queries about this additional information should be directed in the following ways:

Writing to the Scottish Government Energy Consents Unit, 4th Floor, 5 Atlantic Quay, 150 Broomielaw, Glasgow G2 8LU or emailing to energyconsents@scotland.gsi.gov.uk

or

The Highland Council, Planning & Development, Glenurquhart Road, Inverness IV3 5NX

Any subsequent additional information received by Scottish Ministers before determination of the application, if considered to be materially relevant, will be similarly forwarded to The Highland Council to be placed on the planning register and made available for public inspection. However, no further public notice will be issued.

Any representations to the application should quote reference Beauly – Mossford 132kV Transmission Line Replacement and be made in writing to The Scottish Government, Energy Consents Unit, 4th Floor, 5 Atlantic Quay, 150 Broomielaw, Glasgow G2 8LU or emailed to representations@scotland.gsi.gov.uk identifying the proposal and specifying grounds for objection or support, not later than 16/04/2012 . Representations should be dated and should clearly state the name (in block capitals) and full return email or postal address of those making representation. Only representations sent by email to the address stipulated will receive acknowledgement.