Glasgow CityELECTRICITY ACT 1989TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997-4.26484355.857406G2 8LU2012-10-26G28LUTSO (The Stationery Office), St Crispins, Duke Street, Norwich, NR3 1PD, 01603 622211, customer.services@tso.co.uk271642626

Scottish Hydro Electric Transmission Limited

NOTICE OF DECISION
ELECTRICITY ACT 1989
TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997
THE ELECTRICITY WORKS (ENVIRONMENTAL IMPACT ASSESSMENT)(SCOTLAND) REGULATIONS 2000
THE ELECTRICITY (APPLICATION FOR CONSENT) REGULATIONS 1990

Further to the notice of an application for consent to install and keep installed, a 132kV AC double circuit, overhead, steel tower, transmission line between Tower 3 at Corriemoillie, by Lochluichart, Ross-shire (Grid Reference NH 3491 6354) and terminal Tower 97 at the Dunmore Cable Termination Compound, by Beauly, Inverness-shire (Grid Reference NH 5067 4735).

Notice is hereby given that Scottish Hydro Electric Transmission Limited (“the Company”) has been granted consent by Scottish Ministers to install and keep installed the Beauly-Mossford 132kV AC double circuit, overhead, steel tower, transmission line, together with planning permission under section 57(2) of the Town & Country Planning Act (Scotland) 1997.

Copies of the decision statement and consent documentation can be obtained from:

Energy Consents Unit

Scottish Government

4th Floor

5 Atlantic Quay

150 Broomielaw

Glasgow

G2 8LU

Or by email from energyconsents@scotland.gsi.gov.uk

Or on the Energy Consents website: www.scotland.gov.uk/topics/business-industry/energy/energy-consents

Copies of the decision statement and consent documentation have been made available to The Highland Council to be made available for public inspection by being placed on the planning register.