New Roads and Street Works
London Borough of Barnet
NEW ROADS AND STREET WORKS ACT 1991 (“THE ACT”) SECTION 58
NOTICE OF RESTRICTION ON STREET WORKS
- 1 Notice is hereby given by the Council of the London Borough of Barnet (the highway authority and the street authority) that it intends to carry out substantial road works and that the restriction imposed by this notice will apply.
- 2 The streets in which these works are intended to take place; the type of works, details of the estimated area; length and location of work and commencement dates proposed are as per the schedule to this notice. (The schedule is subject to regular review and any revisions will be published and/or circulated as soon as practicable thereafter to all statutory undertakers and other interested parties. In keeping with the normal practice all residents, businesses, traders etc likely to be affected by the work will be notified by circular letters in advance of the start of the scheme.)
- 3 Once the Council’s works relating to any one of the above streets have been completed,
no statutory power to break up or open that street shall be exercisable during the
period of 12 months following completion of those works except:-
- a in the case of emergency works or other works excepted under Section 58 (5) of the Act;
or
- b with the consent of the Council
PROVIDED that, where the Council’s works relate to part, rather than to the whole, of a street, the restriction on breaking up or opening the street shall apply only to the part of the street to which the works relate.
- 4 All applications for consent must be submitted to the Chief Highways Officer, North London Business Park, Oakleigh Road South, London N11 1NP, in writing at least 20 working days before the excavation is proposed to start. The application should be submitted with drawings, extent of work and method of working including proposed traffic management, start and completion dates and the reason for the excavation. The Council may not unreasonably withhold consent.
- 5 Contact details:
Name: M Shan Vaiti/ Mr Kugan Sabanayagam
Tel No: 020 8359 7215/ 7344
E-mail: shan.vaiti@barnet.gov.uk kugan.sabanayagam@barnet.gov.uk
Date: 24 September 2008
Signed Ian Caunce CEng BSc MICE MIHT MIRSO
Chief Highways Officer, Environment and Transport
for and on behalf of the London Borough of Barnet
North London Business Park
Oakleigh Road South,
London
N11 1NP
Schedule
London Borough of Barnet
4th Quarter Planned Highway Maintenance Programme 2008 - 2009
Location | Section | District | Type of Works | Estimated Length (m) | Estimated Area (m2) | Expected start | Expected Completion Date |
GRAHAM PARK WAY | Worst Sections | NW7 / NW9 | Footway Relay | 305 | 1200 | Jan-09 | Mar-09 |
BUNNS LANE | Worst Sections | NW7 | Footway Relay | 250 | 1000 | Jan-09 | Mar-09 |
PARK ROAD | Worst Sections | NEW BARNET | Footway Relay | 180 | 720 | Jan-09 | Mar-09 |
OSIDGE LANE | Worst Sections | N14 | Footway Relay | 210 | 840 | Jan-09 | Mar-09 |
MAYS LANE | Shelford Road to Barnet Lane | BARNET | Footway Relay | 200 | 800 | Jan-09 | Mar-09 |
NORTH END ROAD | Worst Sections | NW11 | Footway Relay | 320 | 1020 | Jan-09 | Mar-09 |
DEANSBROOK ROAD | Worst Sections | EDGWARE | Footway Relay | 240 | 800 | Jan-09 | Mar-09 |
ORCHARD ROAD | Whole Length | BARNET | Footway Relay | 140 | 580 | Dec-08 | Mar-09 |
WOODLANDS | Whole Length | NW11 | Carriageway Resurfacing | 320 | 2560 | Jan-09 | Jan-09 |
CLOISTER ROAD | Whole Length | NW2 | Carriageway Resurfacing | 300 | 2880 | Jan-09 | Jan-09 |
WALKS THE | Whole Length | N2 | Carriageway Resurfacing | 51 | 344 | Jan-09 | Jan-09 |
CHURCH LANE | Whole Length | N2 | Carriageway Resurfacing | 586 | 3516 | Jan-09 | Jan-09 |
CARNARVON ROAD | Whole Length | BARNET | Carriageway Resurfacing | 183 | 1281 | Jan-09 | Jan-09 |
GARTH ROAD | Whole Length | NW2 | Carriageway Resurfacing | 213 | 1300 | Jan-09 | Jan-09 |
A5 CRICKLEWOOD BROADWAY | Mora Road to Depot Approach | NW2 | Carriageway Resurfacing | 286 | 2500 | Dec-08 | Dec-08 |
A5 THE HYDE | Woodfield Avenue to Kingsbury Road | NW9 | Carriageway Resurfacing | 327 | 1800 | Jan-09 | Jan-09 |
A5 THE HYDE | Kingsbury Road to Kingsbury Road to | NW9 | Carriageway Resurfacing | 560 | 9400 | Jan-09 | Jan-09 |
A5 THE HYDE | Garrick Road | NW9 | Carriageway Resurfacing | 560 | 9400 | Jan-09 | Jan-09 |
A1003 WOODHOUSE ROAD | Lewes Road to Ashurst Road | N12 | Carriageway Resurfacing | 208 | 3000 | Jan-09 | Jan-09 |
A1000 PRICKLERS HILL & GREAT NORTH ROAD | Lyonsdown Road to Rail Bridge | BARNET | Carriageway Resurfacing | 954 | 9700 | Jan-09 | Jan-09 |